Fabricating Materials for a Public Works Project at a Permanent Offsite Facility? Prevailing Wages N


Bill & Ted's Excellent Adventure

The Case: Sheet Metal Workers’ International Association, Local 104 v. Duncan, Case No. A131489 (August 27, 2014).

The Court: California Court of Appeal for the First District.

The Issue: Whether a contractor fabricating materials on a public works project at a permanent offsite facility, and whose contract expressly stated that the project was subject to prevailing wage requirements, was required to pay prevailing wages?

The Holding: Nope.

The Most Excellent Write-Up: See my esteemed colleagues, Mona Ebrahimi, Maggie Stern and Anthony Bento‘s legal alert, Offsite Fabrication at Permanent Facility Not Subject to Prevailing Wage Law.

Have an excellent Monday.

#SheetMetalWorkersInternational #Local104 #Duncan #Offsite #Prevailingwages